Otto Energy Limited, as operator of the producing Galoc oilfield joint venture offshore the Philippines, provided the following update on the Galoc-5H and Galoc-6H drilling campaign in SC14C, part of the Galoc Phase II development approved in 2012.

Progress

During the period from 0600 hours (AWST) June 26 to 0600 hours (AWST) July 3, 13.375 inch casing was cemented and pressure tested on G-6H. The 17.5 inch hole was drilled to 3,117 feet (950 meters) and 13.375 inch casing was run and cemented on G-5H.

Forward Plan

The forward plan is to run the Blowout Preventer (BOP) with riser and connect to the wellhead on G-6H. Make up 12.25 inch Bottom Hole Assembly (BHA) and run in hole.

WHAT DO YOU THINK?

Generated by readers, the comments included herein do not reflect the views and opinions of Rigzone. All comments are subject to editorial review. Off-topic, inappropriate or insulting comments will be removed.

Related Companies

For More Information on the Offshore Rig Fleet:
RigLogix can provide the information that you need about the offshore rig fleet, whether you need utilization and industry trends or detailed reports on future rig contracts. Subscribing to RigLogix will allow you to access dozens of prebuilt reports and build your own custom reports using hundreds of available data columns. For more information about a RigLogix subscription, visit www.riglogix.com.

Source: http://www.rigzone.com/news/oil_gas/a/127526/Otto_Energy_Updates_on_Galoc_Phase_II_Development?rss=true

nj transit PSEG hocus pocus hocus pocus mta schedule PECO Hurricane Sandy update

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.